Hub selection template

Sheet1

Hub Selection
Note: If $/mile/ton is not given then use 1 for each location.
$/ton/mile Tons X cord Y Cord distance Cost Optimal Solution
A 1.5 500 650 750 158.1129258317 118584.694373798 X 500.0011930466
B 1.3 1000 550 1050 353.5537685958 459619.899174538 Y 699.9994477268
C 1.95 1200 750 950 353.5529375002 827313.873750477 Objective 7229742.35689002 Minmum Cost
D 1.1 800 850 550 380.7873411593 335092.860220182
E 1.85 700 650 350 380.787677711 493120.042635736
F 1.25 1400 780 980 395.9793443712 692963.852649541
G 1.55 1000 400 800 141.4225903655 219205.015066481 400 7229742.35689002
H 1.05 900 950 250 636.3948689406 601393.151148884 800 9292587
P1 2 4000 500 700 0.0013146733 10.5173861716 9292586.71681756 2062844.64310998
P2 2 2000 300 400 360.5553298129 1442221.31925143
P3 2 1500 900 150 680.0723770776 2040217.13123278
15000
Approximate Solution using Center of gravity Method
X 613.8 Y 631.4666666667